Love the Bright Orange Road Construction Barrels? You’re in Luck!
February’s weather cost the Georgia DOT contractor two weeks of work on flyover ramps linking Interstate 85 to SR-400. Traffic on Cheshire Bridge Road and Lindbergh Drive will keep dodging construction barrels at least until April.
Loren Bartlett, DOT project manager, says the project continues to move as fast as possible because of financial penalties in the state contract with Archer Western.
“The contract calls for $1869 daily penalties,” she says, noting it was to be complete by January 14, 2014.
What about the two weeks when ice and snow kept Atlanta immobile?
The Department will consider inclement weather as
reason to be exempt from daily fines. The project construction budget is at $21 million. (AW’s contract is $21,423,500 for better accuracy.)
The nature trail along the creek is coming into clearer view as the ramps above are connected. By March 1 contractors laid beds of large stone along the creek, topping it with smaller gravel and compacting them into a smooth trail. The largest bridge across the main span of the North Fork is in place. Several smaller culverts across feeder creeks will be part of the trail. At least one is poured on site, and others are expected in early March. Decorative fences and approaches leading to the main bridge are likely to be among the last elements to be built.
Sally Sears