LaVista/Briarcliff Intersection Improvements

Barbara_WheelerBelow is a report from our DeKalb Transportation Coordinator, Barbara Wheeler, following her conversation with Dave Pelton, Supervising Engineer at DeKalb County Transportation.

The current proposal for Briarcliff and LaVista is at a standstill, the county is working on a concept to improve the intersection, but there are some objections by the commissioners to making the intersection any bigger.

Among the constraints, the church on the corner, Peachtree Baptist Church, is historic and cannot be altered, and the Whole Foods retaining wall is also immovable.

The commissioners inquired if the intersection could be converted to a roundabout, but the available space is not adequate for a large roundabout.

GDOT has set aside some money to improve the intersection, but the commissioners are not supportive of this current concept, so it is not moving forward.

The county would welcome any creative ideas for improvements that make the intersection flow better AND be more pedestrian friendly which Mr. Pelton believes is the commissioners’ point of view (hence the roundabout idea).

Click HERE to see the current concept drawing.

Advertisements

March 25, 2014 at 6:42 pm 1 comment

What’s Up With Trail Under SR-400 & I-85

Love the Bright Orange Road Construction Barrels? You’re in Luck!

February’s weather cost the Georgia DOT contractor two weeks of work on flyover ramps linking Interstate 85  to SR-400. Traffic on Cheshire Bridge Road and Lindbergh Drive will keep dodging construction barrels at least until April.

Loren Bartlett, DOT project manager, says the project continues to move as fast as possible because of financial penalties in the state contract with Archer Western.

“The contract calls for $1869 daily penalties,” she says, noting it was to be complete by January 14, 2014.

What about the two weeks when ice and snow kept Atlanta immobile?

 

The Department will consider inclement weather as
reason to be exempt from daily fines.  The project construction budget is at $21 million. (AW’s contract is $21,423,500 for better accuracy.)

The nature trail along the creek is coming into clearer view as the ramps above are connected. By March 1 contractors laid beds of large stone along the creek, topping it with smaller gravel and compacting them into a smooth trail. The largest bridge across the main span of the North Fork is in place.  Several smaller culverts across feeder creeks will be part of the trail. At least one is poured on site, and others are expected in early March.  Decorative fences and approaches leading to the main bridge are likely to be among the last elements to be built.

Sally Sears 

Executive Director, The South Fork Conservancy

March 3, 2014 at 3:05 pm Leave a comment