DeKalb County Addresses North Druid Hills Road Construction

March 14, 2012 at 9:45 am 2 comments

By Jonathan Cribbs for North Druid HIlls – Briarcliff Patch

The widening project along North Druid Hills Road will cost $2.6 million and last about 15 months

A number of people have emailed me over the last few days about this construction on North Druid Hills Road. I got a response today from DeKalb County spokesman Burke Brennan, and, before I write a more detailed story, I figured I would pass his email along to you guys who want to know more about it.

Here is Brennan’s email to me:

The project will widen North Druid Hills Road from Briarcliff Road to Woodcliff Drive in order to extend the left-turn lane to Briarcliff Road southbound. North Druid Hills Road will also be widened from Briarcliff Road to the west, toward Interstate 85, in order to provide a third westbound receiving lane for the double left turn lane from Briarcliff Road northbound. Briarcliff Road will also be widened to provide an additional southbound through lane from North Druid Hills Rd to Sheridan Drive.

The project is expected to ease traffic congestion and reduce delays for drivers who use this intersection every day.  In addition, new ADA compliant sidewalks, upgraded traffic signals, and crosswalks will enhance the safety of pedestrians who pass through the area.

Funding for the project comes from revenue from the 2005 bond referendum for infrastructure projects. Construction is estimated to take approximately 15 months at a cost of approximately $2.6 million. The contractor for the project is Desmear Systems, Inc.

Now, does that mean motorists on that road can expect the same kind of delays for the next 15 months? I’m not sure. Either way, I doubt it’s going to be pretty considering how awfully congested that road is most of the time anyway. (It’s a primary reason I grocery shop at 1 in the morning.) It’s going to be split into phases, and Brennan is currently looking into that for me now. Like I said, I’ll have a more detailed story on it for you guys once I get all the information. This is for those of you wondering what the heck is going on out there.

UPDATE: Brennan just emailed me back regarding the phases.

Here’s his response:

It will be up to the contractor to decide how to phase his work.   However, he is not going to be working in the road all of the time, so  his impacts to traffic are going to be variable during the life of the  project.

Advertisements

Entry filed under: Traffic. Tags: , , , .

Long-awaited Buckhead interchange revamp starts Clifton Corridor Transit Initiative Announces Locally Preferred Alternative

2 Comments Add your own

  • 1. jessica  |  March 14, 2012 at 1:01 pm

    I can’t believe that they aren’t giving this more media attention! Terrible!

    Reply
  • 2. bob  |  March 19, 2012 at 1:12 pm

    REALLY POOR PLANNING not one bit of information was given to any of the businesses around the intersection either!

    I am sure it will be a huge slow moving progress.

    Work at night so its clear during the day.

    Reply

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

Trackback this post  |  Subscribe to the comments via RSS Feed


Calendar

March 2012
M T W T F S S
« Feb   Apr »
 1234
567891011
12131415161718
19202122232425
262728293031  

Most Recent Posts


%d bloggers like this: